Overall Project Plan (example)
| ID | Task Name | Duration |
| 1 | Phase 0 - Project Planning | 288 hrs |
| 21 | Project Communications Plan | 88 hrs |
| 34 | Develop Project Plan | 128 hrs |
| 44 | Develop Business Case for Architecture | 96 hrs |
| 50 | Develop Project Proposal | 272 hrs |
| 65 | Phase Wrap-up | 1.11 days |
| 77 | Phase 1 - Business Focus of the Architecture Start up | 2.44 days |
| 87 | Execute Communication Plan | 280 hrs |
| 98 | Interview process | 3.23 days |
| 131 | Prepare Architecture Requirements Report & Matrix 1 (BD x AR) | 12.85 days |
| 147 | Prepare Technology Trends (TT) Report | 5.81 days |
| 157 | Present Phase 1 Deliverable For Commitment | 4.89 days |
| 178 | Phase Wrap-up | 1.11 days |
| 188 | Phase 2 - Technical Focus | . |
| 200 | Component Development (for each component) | 35 days |
| 201 | Phase Wrap-up | 1.11 days |
| . | Phase Wrap-up (project) | . |