| Sequence |
Task w/I
total project |
Task
Description |
Duration |
Dependency |
| 0 | 0 | Business Driven Architecture Project (BDAP) | 85.3d | |
| 1 | 617 | Enterprise Wide Technical Architecture - BDAP | 85.3d | |
| 2 | 618 | Phase 1 | 27.5d | |
| 3 | 619 | Begin Phase 1 (Project Mgt./Communication) | 0d | |
| 5 | 620 | Initiate Enabling Group For Coordinate & Communicate | 1d | |
| 6 | 621 | Define Mission Of The Team | 2.5h | 3 |
| 7 | 622 | Define Goals Of The Team | 2.5h | 6 |
| 8 | 623 | Define Deliverable Of The Team | 2.5h | 7 |
| 9 | 624 | Assign The Team | 2h | 8 |
| 10 | 625 | Assign Roles & Responsibilities | 3h | 9 |
| 11 | 628 | Initiate Enabling Group For Research & Educate (Research
Business & Tech. trends | 1.05d | 5 |
| 12 | 629 | Define Mission Of The Team | 2.5h | 3 |
| 13 | 630 | Define Goals Of The Team | 2.5h | 12 |
| 14 | 631 | Define Deliverable Of The Team | 2h | 13 |
| 15 | 632 | Assign The Team | 3h | 14 |
| 16 | 633 | Assign Roles & Responsibilities | 2.5h | 15 |
| 23 | 636 | Prepare Business Driver Report | 11.9d | 11 |
| 24 | 637 | Synchronize Business Driver Understanding (Interview Teams) | 1.35d | 10 |
| 25 | 638 | Define Business Driver Definition | 2h | |
| 26 | 639 | Assign BDAP Team Members to LOBs | 2.5h | |
| 28 | 640 | Identify BD Process Owner (LOB BD) | 1h | 27 |
| 27 | 641 | Identify LOB BD Contacts | 2.5h | 26 |
| 33 | 642 | Determine BD Training Strategy & Develop Training Content | 2h | 32 |
| 34 | 643 | Train BDAP Interviewers | 2h | 26 |
| 35 | 645 | Determine Phase 1 Time lines & Strategy | 6h | |
| 36 | 646 | Outline BD Report | 3h | 34 |
| 37 | 647 | Meta Group Reviews BD Report Outline | 2h | 36 |
| 39 | 648 | Prepare for LOB Interview | 3.9d | 26 |
| 40 | 649 | Required Preparation | 3.9d | |
| 41 | 650 | Review EDD Strategic Plan | 5h | |
| 42 | 651 | Review LOB Annual Business Plans | 4.5h | 41 |
| 43 | 652 | Review Previous Strategic I/T Efforts | 4h | 42 |
| 44 | 653 | Interview BCT Contact | 4.5h | 43 |
| 45 | 654 | Review Meta Box LOB Info | 5h | 44 |
| 46 | 655 | Finalize Preparation | 2.55d | |
| 47 | 656 | Outline Research Information Report | 5h | 45 |
| 48 | 657 | Hold Planning Session w/ BU Process Owner | 1.7d | |
| 49 | 658 | Validate Understanding Of Business | 10h | 47 |
| 50 | 659 | Prepare For BD Discovery Process | 10h | 49 |
| 51 | 660 | Finalize Research Information Report (Meta Review) | 5h | 50 |
| 52 | 661 | Conduct Interview Process | 3.45d | 39 |
| 53 | 662 | Prepare Customized Questionnaire & Strategy | 6.5h | 51 |
| 54 | 663 | Submit Questionnaire To Meta For Review | 2h | 53 |
| 29 | 664 | Finalize Questionnaire | 3h | 28 |
| 30 | 665 | Write Interview Letter | 1h | 29 |
| 31 | 666 | Schedule Interviews | 2h | 30 |
| 55 | 667 | Deliver Interview Letter With Questionnaire | 4h | 54 |
| 32 | 668 | Publish Interview Letter | 1h | 31 |
| 56 | 669 | Prepare and Perform Interview & Receive BD | 32h | 55 |
| 59 | 670 | Update BD Report | 4.5h | 58 |
| 60 | 671 | Analyze Information (Core Team) | 1d | 52 |
| 61 | 672 | Assign Debriefing Assignments | 1h | |
| 62 | 673 | Prepare for Debrief | 9.5h | 61 |
| 63 | 674 | Review LOB BD Report w/ Interviewer | 3h | 62 |
| 64 | 675 | Update LOB BD Report | 3h | 63 |
| 65 | 676 | Confirm & Prioritize LOB BD Report | 2.75d | 60 |
| 66 | 677 | Define Time lines for Modifications & Prioritization from
LOB | 5h | 64 |
| 67 | 678 | Prepare Thank You Letter | 1h | 66 |
| 68 | 679 | Attach LOB BD To Thank You Letter | 1h | 67 |
| 69 | 680 | Deliver Thank You Letter & Draft BU BD Report | 4h | 68 |
| 71 | 681 | Modify & Prioritize Business Drivers (LOB) | 8h | 70 |
| 72 | 682 | Received LOB Prioritized Modified BD Report | 4h | 71 |
| 73 | 683 | Finalize LOB BD Report (Meta Review) | 2h | 72 |
| 74 | 684 | Deliver Final LOB BD Report | 4h | 73 |
| 75 | 685 | Assign LOB Owner To Each Business Driver | 3h | 74 |
| 77 | 686 | Prepare Architecture Requirements Report & Matrix 1 (BD x
AR) | 7d | 23 |
| 78 | 687 | Develop Common Understanding of AR | 1.3d | |
| 79 | 688 | Define Mission (Purpose of AR) | 2.5h | |
| 80 | 689 | Train Core Team on AR Facilitation | 7h | 79 |
| 81 | 690 | Outline Architecture Requirement Document & Matrix | 5h | 80 |
| 82 | 691 | Develop AR Report & Matrix 1 (BD x AR) | 4.55d | 78 |
| 83 | 692 | Coordinate AR Development Session | 3h | |
| 84 | 693 | Identify Information Required to Support BD | 12h | 83 |
| 85 | 694 | Identify the Processes That Generates The Required Information | 11.5h | 84 |
| 86 | 695 | Derive AR From Data & Process Input (See EAS Process Model,
Pag 10.) | 23.5h | |
| 88 | 696 | Update AR Report & Matrix 1 | 10h | 87 |
| 89 | 697 | Confirm Architecture Requirement (AR) | 1.15d | 82 |
| 90 | 698 | Define Response Time lines | 3h | 88 |
| 91 | 699 | Prepare Thank You Letter (Attach LOB AR Report) & Matrix 1 | 1h | 90 |
| 95 | 700 | Receive LOB AR Edits (Report & Matrix) | 6h | 94 |
| 97 | 701 | Finalize LOB AR Report & Matrix 1 (BD x AR) (Meta Review) | 5h | 96 |
| 98 | 702 | Prepare Technology Trends Report | 2.85d | 89 |
| 99 | 703 | Develop T.T. Report Meta Trends) | 2.85d | |
| 100 | 704 | Select Tech. Trend Report Author | 1h | |
| 101 | 705 | Prepare First Draft Of Tech. Trend Report | 10h | 100 |
| 102 | 706 | Get BU I/T Involvement & Agreement W/ T.T. Report | 12h | 101 |
| 104 | 707 | Prepare Second Draft Tech. Trend Report | 4h | 103 |
| 105 | 708 | Review T.T. Report | 2h | 104 |
| 107 | 709 | Finalize T.T. Report (Meta Review) | 1h | 106 |
| 108 | 710 | Present Phase 1 Deliverable For Commitment | 3.35d | 98 |
| 109 | 711 | Give Presentation | 3.35d | |
| 111 | 712 | Coordinate Meeting Room & Date | 4h | 110 |
| 112 | 713 | Invite Participants (ITSMT,ITEI,ITDQC) | 2h | |
| 113 | 714 | Prepare Presentation/Deliverable | 18h | 112 |
| 115 | 715 | Deliver Phase 1 Deliverable Hard Copy To Attendees | 1h | 114 |
| 116 | 716 | Execute Presentation Preparation | 3h | 115 |
| 118 | 717 | Cleanse Phase 1 Deliverable | 5h | 117 |
| 125 | 718 | Publish Phase 1 Deliverable | 2h | 124 |
| 121 | 719 | Obtain Commitment to Business Alignment | 0.95d | 114 |
| 110 | 721 | Define Time lines For Response | 1h | 107 |
| 124 | 722 | Coordinate and Consolidate LOB Responses | 1h | 123 |
| 136 | 724 | Phase 2 | 54.55d | 126 |
| 137 | 725 | Begin Phase 2 | 0d | 108 |
| 139 | 726 | Initiate Enabling Group For Coordinate & Communicate | 1.1d | |
| 140 | 727 | Define Mission Of The Team | 3h | |
| 141 | 728 | Define Goals Of The Team | 2h | 140 |
| 142 | 729 | Define Deliverable Of The Team | 3h | 141 |
| 143 | 730 | Assign The Team | 2h | 142 |
| 144 | 731 | Assign Roles & Responsibilities | 3h | 143 |
| 145 | 734 | Initiate Enabling Group For Research & Educate | 1.05d | 139 |
| 146 | 735 | Define Mission Of The Team | 2h | 144 |
| 147 | 736 | Define Goals Of The Team | 3h | 146 |
| 148 | 737 | Define Deliverable Of The Team | 2h | 147 |
| 149 | 738 | Assign The Team | 3h | 148 |
| 150 | 739 | Assign Roles & Responsibilities | 2h | 149 |
| 158 | 742 | Prepare Principles - Conceptual Architectures) | 9.35d | 150 |
| 159 | 743 | Develop Common Understanding Of Principles | 5.1d | |
| 160 | 744 | Assemble Principles Team | 2h | |
| 161 | 745 | Define Purpose Of Principle | 4h | 160 |
| 165 | 746 | Define Principles | 4h | 164 |
| 162 | 747 | Train Team - | 4.5h | 161 |
| 163 | 748 | Define Roles & Responsibilities & Time frames | 4h | 162 |
| 166 | 749 | Outline Principles | 3h | 165 |
| 167 | 750 | Develop Checkpoint with Josetta | 2h | 166 |
| 169 | 751 | Develop Principles Report | 4.25d | 159 |
| 170 | 752 | Review Principles List | 12h | |
| 172 | 753 | Update Principles Report | 2h | 171 |
| 173 | 754 | Prepare Best Practices Report & Matrix 2A (AR x BP)
Conceptual Architectures) | 10.6d | 150 |
| 174 | 755 | Develop Common Understanding Of Best Practices | 5.1d | |
| 175 | 756 | Assemble BP Team | 2h | |
| 176 | 757 | Define Purpose Of BP | 4h | 175 |
| 180 | 758 | Define Best Practice | 4h | 179 |
| 177 | 759 | Train Team - How to Decompose BP From AR | 4.5h | 176 |
| 178 | 760 | Define Roles & Responsibilities & Time frames | 4h | 177 |
| 181 | 761 | Outline BP Report & Matrix 2A | 3h | 180 |
| 183 | 762 | Checkpoint with Josetta | 1h | 182 |
| 184 | 763 | Develop Best Practices Report (includes both CIT & DIT) | 5.5d | 174 |
| 185 | 764 | Review Best Practices List | 12h | |
| 186 | 765 | Update BP Report & Matrix 2A | 2h | 185 |
| 187 | 766 | Analyze AR x BP Matrix | 5h | 186 |
| 188 | 767 | Create Required Best Practices | 37h | 187 |
| 189 | 768 | Update BP Report & Matrix 2A (AR x BP) | 5h | 188 |
| 191 | 769 | Checkpoint with Josetta | 2h | 190 |
| 192 | 770 | Finalize BP Report & Matrix (Meta Review) | 2h | 191 |
| 193 | 771 | Prepare Component Architecture Report & Matrix 2B (BP x CA) | 10.75d | 192 |
| 194 | 772 | Develop Common Understanding Of Component Architecture | 1.35d | |
| 195 | 773 | Validate Phase 0 Component Architecture List | 1h | |
| 196 | 774 | Accept/Modify Applicable Component Architectures | 1.5h | 195 |
| 197 | 775 | Identify Component Architecture Owners | 1h | 196 |
| 198 | 776 | Assemble CA Teams | 1h | 197 |
| 199 | 777 | Define Purpose Of CA | 1h | 198 |
| 200 | 778 | Define CA | 2h | 199 |
| 201 | 779 | Train Team - How to
Decompose CA From BP | 2h | 200 |
| 202 | 780 | Define Roles & Responsibilities & Time frames | 3h | 201 |
| 203 | 781 | Define CA Level Of Detail | 2h | 202 |
| 204 | 782 | Outline CA Report & Matrix 2B | 1h | 203 |
| 205 | 783 | Develop CA Report | 9.5d | |
| 210 | 784 | Governance - Create
Component Architectures (Composition) | 9.5h | 203 |
| 211 | 785 | Update CA Report & Matrix 2B (BP x CA) | 11.5h | 206 |
| 212 | 786 | Analyze CA Report & Matrix 2B | 12h | 211 |
| 215 | 788 | Finalize CA Report & Matrix 2B (Meta Review) | 6h | 214 |
| 247 | 790 | Prepare Base line Report | 52.4d | |
| 248 | 791 | Identify, Collect &
Document Existing Branch Information | 0.3d | 7.3d |
| 249 | 792 | Understand Phase 0 CA Selection | 2h | 194 |
| 250 | 793 | Understand Phase 0 CA Level Of Detail | 3.5h | 249 |
| 251 | 794 | Review Phase 0 CA Report Outline | 2h | 250 |
| 253 | 795 | Identify Target Information (See Meta EAS Process Model Pgs.
13-14) | 5h | |
| 254 | 796 | Collect Target Information | 25h | 253 |
| 256 | 797 | Consolidate Branch Information Collected | 40.5h | 255 |
| 268 | 798 | Update Branch Base line Report | 2h | 256 |
| 257 | 799 | Analyze Branch Information | 2.05d | |
| 258 | 800 | Review Team Must Prepare For Dialog | 6h | 256 |
| 259 | 801 | Review Branch Base line Report | 4.5h | 258 |
| 260 | 802 | Finalize Branch Base line Report | 3h | 259 |
| 261 | 803 | Deliver Branch Base line Report | 2h | 260 |
| 263 | 804 | Cleanse Branch Base line Report | 2h | 262 |
| 264 | 805 | Publish Branch Base line Report | 3h | 263 |
| 265 | 806 | Consolidate Branch Base line Into EDD Base line | 7.55d | 205 |
| 266 | 807 | Receive Branch Reports | 2.5h | 264 |
| 269 | 808 | Consolidate Into EDD Base line | 6h | 268 |
| 270 | 809 | Finalize EDD Base line Report (Meta Review) | 2h | 269 |
| 271 | 810 | Deliver EDD Base line Report | 2h | 270 |
| 272 | 811 | Checkpoint with Josetta | 1h | 271 |
| 273 | 812 | Cleanse EDD Base line Report | 1h | 272 |
| 274 | 813 | Publish EDD Base line Report | 2h | 273 |
| 275 | 814 | Perform Gap Analysis | 10.5d | |
| 277 | 815 | Prepare for ITDQC, ITET Meeting | 4.5h | |
| 281 | 816 | ITDQC - Review EDD Base line Report (Current State) | 1h | 280 |
| 282 | 817 | ITDQC - Review EDD CA Report (Desired State) | 1h | 280 |
| 284 | 818 | Establish Goals Of This Effort | 5h | 282 |
| 285 | 819 | Synchronize Participants Understanding Of Goals | 5h | 284 |
| 286 | 820 | Outline Gap Analysis Report | 5h | 285 |
| 287 | 821 | Analyze Gaps For Potential Opportunities | 12h | 286 |
| 288 | 822 | Research Information | 23h | 287 |
| 293 | 823 | Make Major Decisions & Establish Clear Direction(DIT Mgt.) | 1.5h | 292 |
| 294 | 824 | Update Gap Analysis Report | 4h | 288 |
| 296 | 825 | Checkpoint with Josetta | 2h | 294 |
| 297 | 826 | Review Gap Analysis Report | 12.5h | 296 |
| 298 | 827 | Finalize Gap Analysis Report (Meta Review) | 10.5h | 297 |
| 299 | 828 | Final Buy List | 4.5h | 298 |
| 300 | 829 | Present Phase 2 Deliverable For Commitment | 2.2d | 275 |
| 301 | 830 | Obtain Commitment/Give Presentation | 2.2d | |
| 302 | 831 | Coordinate Meeting Room & Date | 0.5h | |
| 303 | 832 | Invite Participants (ITET, ITDQC) | 0.5h | |
| 306 | 833 | Prepare Presentation | 6h | 305 |
| 307 | 834 | Checkpoint with Josetta | 2h | 306 |
| 308 | 835 | Deliver Phase 2 Deliverable Hard Copy To Attendees | 1h | 307 |
| 310 | 836 | Execute Presentation | 2h | 309 |
| 311 | 837 | Checkpoint with Josetta | 2h | 310 |
| 312 | 838 | Cleanse Phase 2 Deliverable | 2h | 311 |
| 313 | 839 | Publish Phase 2 Deliverable | 3h | 312 |
| 304 | 841 | Define Response Required | 1h | 303 |
| 305 | 842 | Define Time lines For Response | 1h | 304 |
| 314 | 843 | Consolidate LOB Responses | 1h | 305 |
| 315 | 844 | Complete Phase 2 | 0d | 193 |
| 325 | 845 | Phase 3 | 20.7d | 315 |
| 326 | 846 | Begin Phase 3 | 0d | |
| 328 | 847 | Initiate Enabling Group For Coordinate & Communicate | 0.5d | |
| 329 | 848 | Define Mission Of The Team | 2h | |
| 330 | 849 | Define Goals Of The Team | 2h | 329 |
| 331 | 850 | Define Deliverable Of The Team | 2.5h | 330 |
| 332 | 851 | Assign The Team | 2h | 331 |
| 333 | 852 | Assign Roles & Responsibilities | 3h | 332 |
| 334 | 855 | Initiate Enabling Group For Research & Educate | 0.5d | |
| 335 | 856 | Define Mission Of The Team | 2h | 326 |
| 336 | 857 | Define Goals Of The Team | 2h | 335 |
| 337 | 858 | Define Deliverable Of The Team | 2.5h | 336 |
| 338 | 859 | Assign The Team | 2h | 337 |
| 339 | 860 | Assign Roles & Responsibilities | 3h | 338 |
| 346 | 863 | Develop On-going Architecture Improvement Strategy | 8.6d | 327 |
| 347 | 864 | Develop A Common Understanding Of Architecture Improvement
Strategy | 0.5d | |
| 348 | 865 | Understand Vision | 5h | 327 |
| 349 | 866 | Divide Into 3 Sub-Teams | 1h | 348 |
| 350 | 867 | Define The Architecture Improvement Process | 6.95d | |
| 351 | 868 | Discuss Alternatives With Consulting Partners | 4.5h | 348 |
| 352 | 869 | Research Best Practices In Other Companies | 24.5h | 351 |
| 353 | 870 | Develop Recommendation Draft | 11.5h | 352 |
| 354 | 871 | Checkpoint with Josetta | 2h | 353 |
| 355 | 872 | Review & Modify Recommendation | 6h | 354 |
| 357 | 873 | Finalize Recommendation (Meta Review) | 6h | 356 |
| 358 | 874 | Obtain Approval Of Recommendation | 2h | 357 |
| 368 | 876 | Define Architecture Leadership Responsibility (Person Or Team) | 7.35d | |
| 369 | 877 | Discuss Alternatives With Consulting Partners | 5h | 348 |
| 370 | 878 | Research Best Practices In Other Companies | 23.5h | 369 |
| 371 | 879 | Develop Recommendation Draft | 12.5h | 370 |
| 372 | 880 | Checkpoint with Josetta | 2h | 371 |
| 373 | 881 | Review & Modify Recommendation | 7.5h | 372 |
| 374 | 882 | Finalize Recommendation (Meta Review) | 6h | 373 |
| 375 | 883 | Obtain Approval Of Recommendation | 2h | 374 |
| 376 | 885 | Identify Architecture Maintenance Tools (Current & Desired
State) | 8.6d | |
| 377 | 887 | Identify CA Maintenance Tools To Review | 24h | |
| 378 | 888 | Evaluate CA Maintenance Tools | 38h | 377 |
| 379 | 889 | Select CA Maintenance Tools | 10h | 378 |
| 380 | 890 | Checkpoint with Josetta | 2h | 379 |
| 381 | 891 | Install CA Maintenance Tools | 11h | 380 |
| 382 | 892 | Populate CA Maintenance Tools | 24h | 381 |
| 383 | 893 | Prepare Migration Strategy Report | 9.35d | 327 |
| 384 | 894 | Develop Common Understanding Of Migration Strategy Report | 0.7d | |
| 385 | 895 | Define Purpose Of Migration Plan | 5h | |
| 386 | 896 | Outline Migration Strategy Report | 3.5h | 385 |
| 387 | 897 | Develop Migration Strategy Report | 8.65d | 384 |
| 388 | 899 | Review The Component Architectures | 12.5h | |
| 389 | 900 | Identify Key Opportunities For Improvements | 22.5h | 388 |
| 390 | 901 | Provide Recommendation For Strategic Implementation | 47.5h | 389 |
| 391 | 902 | Draft Migration Strategy Report | 12h | 390 |
| 392 | 903 | Checkpoint with Josetta | 3h | 391 |
| 393 | 904 | Modify Migration Strategy Report | 6h | 392 |
| 394 | 905 | Finalize Migration Strategy Report (Meta Review) | 12h | 393 |
| 395 | 906 | Present Phase 3 Deliverable For Commitment | 3.4d | 383 |
| 396 | 907 | Give Presentation | 3.15d | |
| 397 | 908 | Coordinate Meeting Room & Date | 1h | |
| 398 | 909 | Invite Participants (ITSMT,ITEI,ITDQC) | 1h | 397 |
| 399 | 910 | Prepare Presentation | 17h | 398 |
| 400 | 911 | Checkpoint with Josetta | 2h | 399 |
| 401 | 912 | Deliver Phase 3 Deliverable Hard Copy To Attendees | 1h | 400 |
| 404 | 913 | Execute Presentation(Div. Chiefs) | 4h | 403 |
| 405 | 914 | Cleanse Phase 3 Deliverable | 5h | 404 |
| 406 | 915 | Publish Phase 3 Deliverable | 2h | 405 |
| 407 | 916 | Obtain Commitment to Technology Alignment | 0.25d | 406 |
| 408 | 917 | Define Response Required | 1.5h | |
| 409 | 918 | Define Time lines For Response | 1.5h | 408 |
| 410 | 919 | Consolidate LOB Presentation Concerns and Responses | 3h | 402 |
| 411 | 920 | Complete Phase 3 | 0d | 395 |
| 421 | 921 | Complete First Iteration of BDAP | 0d | 420 |
| 119 | 923 | Deliver Phase 1 Deliverable Hard Copy To Attendees | 4h | 118 |
| 123 | 925 | Cleanse Phase 1 Deliverable | 4.5h | 122 |
| 214 | 926 | Update CA Report & Matrix 2B (BP x CA) | 12h | 213 |
| 58 | 934 | Interview for BD | 1h | 57 |
| 70 | 936 | Review Business Drivers (Executives Only) | 3h | 69 |
| 87 | 938 | Conduct Interviews if necessary (Executives Only) | 1h | 86 |
| 94 | 939 | Review AR (Report and Matrix) | 2.5h | 93 |
| 92 | 940 | (Attach LOB AR Report) & Matrix 1 | 1h | 91 |
| 93 | 941 | Deliver LOB AR | 1h | 92 |
| 96 | 942 | Checkpoint with Josetta | 1.5h | 95 |
| 103 | 944 | Get BU I/T Involvement & Agreement W/ T.T. Report | 1h | 102 |
| 117 | 946 | Execute Presentation Delivery | 1h | 116 |
| 120 | 947 | Execute Presentation | 1h | 119 |
| 122 | 951 | Respond to Phase 1 deliverable | 2h | |
| 168 | 953 | Checkpoint with Josetta | 1h | 167 |
| 164 | 954 | Define Principles | 47.5h | 163 |
| 179 | 958 | Define Best Practice | 47.5h | 178 |
| 208 | 968 | Infrastructure - Create Component Architectures (Composition) | 29h | 203 |
| 207 | 969 | Data - Create Component Architectures (Composition) | 18.5h | 206 |
| 206 | 970 | Applications - Create Component Architectures (Composition) | 63.5h | 203 |
| 213 | 971 | Checkpoint with Josetta | 2h | 212 |
| 217 | 972 | Preliminary Buy-in (Josetta ITET) | 1h | 216 |
| 216 | 973 | Prepare Preliminary Buy-in (Josetta ITET) | 3h | 215 |
| 255 | 974 | Collect Target Information | 5h | 254 |
| 262 | 975 | Review Branch Base line Report | 2.5h | 261 |
| 278 | 976 | Checkpoint with Josetta | 1h | 277 |
| 279 | 977 | ITET - Review EDD Base line Report (Current State) | 2h | 277 |
| 280 | 978 | ITET - Review EDD CA Report (Desired State) | 2h | 279 |
| 291 | 980 | Make Major Decisions & Establish Clear Direction(ITB) | 2.5h | 288 |
| 290 | 981 | Make Major Decisions & Establish Clear Direction (internal) | 24h | 288 |
| 309 | 982 | Execute Presentation | 2.5h | 308 |
| 356 | 984 | Review Presentation | 2h | 354 |
| 402 | 986 | Execute Presentation (ITET) | 4h | 401 |
| 403 | 987 | Execute Presentation(ITDQC) | 4h | 402 |
| 417 | 988 | ID and inventory critical work papers | 4.5h | 411 |
| 412 | 989 | Project Wrap up | 1.45d | 411 |
| 418 | 990 | Key factors/Project debrief | 2h | 417 |
| 419 | 991 | Architecture next steps (6 month plan) | 8.5h | 418 |
| 420 | 992 | Project close | 10h | 419 |
| 276 | 993 | Validate Base line Components | 0.8d | |
| 283 | 994 | Develop draft Gap Analysis | 6.65d | |
| 289 | 995 | Negotiate Decisions and Establish Direction | 2.85d | |
| 295 | 996 | Finalize Gap Analysis | 2.7d | |
| 218 | 997 | Develop Buy List process | 3.1d | |
| 219 | 998 | Determine process to be used (Consensus, research, baseline) | 20h | 137 |
| 220 | 999 | Develop process for driving buy lists | 20h | 219 |
| 17 | 1005 | Execute Communication Plan | 19.35d | 4 |
| 38 | 1008 | Check Point with Josetta | 1.5h | 37 |
| 76 | 1009 | Check Point with Josetta | 1.5h | 75 |
| 106 | 1011 | Checkpoint with Josetta | 1h | 105 |
| 114 | 1012 | Checkpoint with Josetta | 1h | 113 |
| 182 | 1013 | Prepare for Checkpoint with Josetta | 2h | 181 |
| 190 | 1014 | Prepare for Checkpoint with Josetta | 5h | 189 |
| 292 | 1015 | Make Major Decisions & Establish Clear Direction(DIT tech.) | 1h | 291 |
| 126 | 1016 | Complete Phase 1 | 0d | 124 |
| 57 | 1017 | Train LOB Interviewees | 1h | 56 |
| 171 | 1021 | Map Principles to Architectural Requirements | 4.2d | 170 |
| 209 | 1022 | Security - Create Component Architectures (Composition) | 21.5h | |
| 221 | 1049 | Develop Buy List Report | 52.4d | 220 |
| 222 | 1050 | Data Domain | 4.6d | |
| 223 | 1051 | Data Transaction Data | 21.5h | 188 |
| 224 | 1052 | Data Data Warehouse | 22h | 223 |
| 225 | 1053 | Application Domain | 10.95d | |
| 226 | 1054 | Application Collaborate/Groupware | 18h | 188 |
| 227 | 1055 | Application Intranet | 21.5h | 226 |
| 228 | 1056 | Application Intranet/E-Commerce | 22.5h | 227 |
| 229 | 1057 | Application Components | 17h | 228 |
| 230 | 1058 | Applications Applications | 18.5h | 229 |
| 231 | 1059 | Applications Middleware | 18h | 230 |
| 232 | 1060 | Infrastructure Domain | 8d | |
| 233 | 1061 | Infrastructure Platform | 20h | 188 |
| 234 | 1062 | Infrastructure Network | 19h | 233 |
| 235 | 1063 | Infrastructure - Systems Management | 21.5h | 234 |
| 236 | 1064 | Governance Domain | 1.55d | |
| 237 | 1065 | Governance | 18h | 188 |
| 238 | 1066 | Security Domain | 1.55d | |
| 239 | 1067 | Security | 18h | 188 |
| 240 | 1068 | Update Report | 12h | 220 |
| 241 | 1069 | Analyze Report | 10.5h | 240 |
| 242 | 1070 | Checkpoint with Josetta | 2h | 241 |
| 243 | 1071 | Update Report | 12h | 242 |
| 244 | 1072 | Finalize Report (Meta
Review) | 6.5h | 243 |
| 245 | 1073 | Preliminary Buy-in (Josetta ITET) | 3h | 244 |
| 246 | 1074 | Preliminary Buy-in (Josetta ITET) | 1h | 245 |
| 19 | 1081 | Execute Communication Plan | 90h | 11 |
| 22 | 1082 | Brief ITSMT Wrap up | 1h | 21 |
| 21 | 1083 | Brief ITSMT Status | 2h | 20 |
| 20 | 1084 | Brief ITSMT on project | 2h | 11 |
| 4 | 1085 | Project Start up | 2.05d | 3 |
| 138 | 1086 | Project Start-up | 2.15d | 137 |
| 151 | 1088 | Execute Communication Plan | 52.4d | 137 |
| 18 | 1093 | Communication Plan | 19.35d | |
| 152 | 1094 | Communication Plan | 52.4d | |
| 153 | 1095 | Execute Communication Plan | 200h | 145 |
| 154 | 1096 | Brief ITSMT on project | 2h | 145 |
| 155 | 1097 | Brief ITSMT Status | 1.5h | 154 |
| 157 | 1098 | Brief ITSMT Wrap up | 2h | 156 |
| 327 | 1100 | Project start-up | 0.5d | 326 |
| 340 | 1102 | Execute Communication Plan | 20.2d | 326 |
| 341 | 1103 | Communication Plan | 20.2d | |
| 342 | 1104 | Execute Communication Plan | 95h | 334 |
| 343 | 1105 | Brief ITSMT on project | 1.5h | 334 |
| 344 | 1106 | Brief ITSMT Status | 1.5h | 343 |
| 345 | 1107 | Brief ITSMT Wrap up | 1h | 344 |
| 413 | 1108 | Review Phase | 0.35d | |
| 414 | 1109 | Develop +/- chart | 2h | |
| 415 | 1110 | Discuss what can be done to accelerate the Project | 2.5h | 414 |
| 127 | 1117 | Phase Wrap-up | 1.05d | 126 |
| 128 | 1118 | Review Phase | 0.45d | |
| 129 | 1119 | Develop +/- chart | 2h | |
| 130 | 1120 | Discuss what can be done to accelerate the Project | 3h | 129 |
| 131 | 1121 | Modify next phase | 0.6d | |
| 132 | 1122 | Review Project Plan | 2h | 130 |
| 133 | 1123 | Delete unnecessary tasks | 1.5h | 132 |
| 134 | 1124 | Add New tasks | 2h | 133 |
| 135 | 1125 | Advise Project Sponsor | 1h | 134 |
| 316 | 1126 | Phase Wrap-up | 0.8d | 315 |
| 317 | 1127 | Review Phase | 0.45d | |
| 318 | 1128 | Develop +/- chart | 2h | |
| 319 | 1129 | Discuss what can be done to accelerate the Project | 3h | 318 |
| 320 | 1130 | Modify next phase | 0.35d | |
| 321 | 1131 | Review Project Plan | 2h | 319 |
| 322 | 1132 | Delete unnecessary tasks | 1h | 321 |
| 323 | 1133 | Add New tasks | 2.5h | 322 |
| 324 | 1134 | Advise Project Sponsor | 1h | 323 |
| 416 | 1138 | Review Project | 1.45d | |
| 156 | 1140 | Brief ITSMT Status | 1h | 155 |
| 267 | 1178 | BDAP review of product | 4h | 266 |
| 252 | 1179 | Independent Team Analysis of Baseline | 7.5d | |
| 359 | 1181 | Develop Governance guidelines | 7.75d | |
| 361 | 1190 | Discuss Alternatives With Consulting Partners | 5h | |
| 362 | 1191 | Research Best Practices In Other Companies | 24h | 361 |
| 363 | 1192 | Develop Recommendation Draft | 12.5h | 362 |
| 364 | 1193 | Checkpoint with Josetta | 2h | 363 |
| 365 | 1194 | Review & Modify Recommendation | 7.5h | 364 |
| 366 | 1195 | Finalize Recommendation (Meta Review) | 6h | 365 |
| 367 | 1196 | Obtain Approval Of Recommendation | 2h | 366 |
| 360 | 1198 | Define compliance controls and procedures | 5h | |